Big progress this week with the roof:  it appears to be finished!  There are some slight areas where we are unhappy with the appearance, but overall we are happy that the roof is on and it doesn't appear to be leaking.  The roofers fixed some of our big issues, namely the way the dormers tie into the main roof, and the parallel lines of the roofing panels on the dormers. 
Picture
Picture
Dormer tie in to the roof that needs some work.
Picture
Working on the valley between stairs and dormer. Main source of leaking.
Picture
The working solution to the chimney box: a custom stainless steel cap. Chris is still concerned that the underlayment is touching the chimney pipe.
Picture
Picture
Picture
Picture
The drywall guys were able to tape and mud most of the drywall that they put up over the weekend.  This is excellent in that the house is really starting to come together inside.  Unfortunately our only source of heat is two space heaters, so things are drying VERY slowly.  
Picture
Picture
Picture
Broken toilet seat lid, drywall mud all over the place, and a large electric bill, but we have walls!!
0 Comments



Leave a Reply.

    Categories

    All
    Grounds
    Kitchen

    Archives

    April 2017
    March 2016
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014

Powered by Create your own unique website with customizable templates.